Title: Request for approval of a change in contract with Unitas Construction, Inc. in connection with Peek Road from North of Grand Ventana Drive to North of Stockdick School Road, adding 25 calendar days, with no change in the amount, Job No. 20/0204-3, UPIN 17103N301003, Precinct 4, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 20/0204
Vendor/Entity Legal Name (if applicable): Unitas Construction, Inc.

MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Unitas Construction, Inc. in connection with Peek Road from North of Grand Ventana Drive to North of Stockdick School Road, adding 25 calendar days, with no change in the amount, Job No. 20/0204-3, UPIN 17103N301003, Precinct 4, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:

Project includes construction of a 4-lane concrete boulevard with 32' median and underground storm sewer system. Change includes 20 days for fill in the ditches on east side of the roadway and 5 days at the driveway in front of the school on Peek Road.

Expected Impact:

Additional time allows the Contractor to complete additional work without penalty.

Alternative Options:

Maintain the original scope of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
09/15/2020
18.d.11.j
Contract Award
01/04/2022
39
Contract Amendment for additional funds and extension of project term
07/19/2022
30
Contract Amendment for additional funds and extension of project term

Location:
Address (if applicable): Peek Road.