File #: 22-5719    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/15/2022 In control: Commissioners Court
On agenda: 9/27/2022 Final action: 9/27/2022
Title: Request for approval of change in contract No. 5 with Sprint Sand & Clay, LLC, for the South Belt Stormwater Detention Basin Excavation, Phase 3, adding 26 calendar days and resulting in an addition of $52,208 to the contract amount. (Clear Creek Watershed, Bond ID C-05, Project ID A520-03-00-E003, Job No. 19/0360, Precincts 1 & 2, MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
Attachments: 1. 092722 CIC NO. 5 SPRINT SAND CLAY PCT 1 backup
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): A520-03-00-E003
Vendor/Entity Legal Name (if applicable): Sprint Sand & Clay, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 5 with Sprint Sand & Clay, LLC, for the South Belt Stormwater Detention Basin Excavation, Phase 3, adding 26 calendar days and resulting in an addition of $52,208 to the contract amount. (Clear Creek Watershed, Bond ID C-05, Project ID A520-03-00-E003, Job No. 19/0360, Precincts 1 & 2, MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:
This change in contract is needed for two added interceptor structures to help improve drainage of the road ditch along the north and east boundaries of the Rev. Lawson Basin at Adair Park. The change also adds a pay item for culverts for the trail connectors to cross the existing road ditches. 3 days will be added for the added scope, and 23 days added due to Inclement Weather for a total of 26 days added to the contract.

Expected Impact:
This RCA is required to complete the District construction contract under original or needed revised scope.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Gove...