Legislation Details

File #: 26-5520    Version: 1 Name:
Type: Contract - Renewal Status: Passed
File created: 8/13/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of a renewal option with Ceballos Construction, LLC (Primary); and Specialty Construction TX, LLC (Secondary) for concrete channel lining repairs (North) for the Flood Control District for the period of February 1, 2027 - January 31, 2028, at a cost of $3,353,813, and for the County Clerk to execute any applicable bonds to be received (250338), MWBE Contracted Goal: 19.11%, MWBE Current Participation: 17.17%.
Attachments: 1. 26-5520 Renewal Job No. 250338 - Multiple Vendors
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Marcus Stuckett

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Renewal

Project ID (if applicable): 250338
Vendor/Entity Legal Name (if applicable): Ceballos Construction, LLC (Primary) ; Specialty Construction TX, LLC (Secondary)

MWBE Contracted Goal (if applicable): 19.11%
MWBE Current Participation (if applicable): 17.17%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Ceballos Construction, LLC (Primary); and Specialty Construction TX, LLC (Secondary) for concrete channel lining repairs (North) for the Flood Control District for the period of February 1, 2027 - January 31, 2028, at a cost of $3,353,813, and for the County Clerk to execute any applicable bonds to be received (250338), MWBE Contracted Goal: 19.11%, MWBE Current Participation: 17.17%.
end

Background and Discussion:
Contract renewal for year 2 (renewal 1) of the Concrete Channel Lining Repairs - North contract at a cost of $3,353,813. These services will provide support for infrastructure maintenance work that will be executed as a result of the passage of the "Maintenance Matters" Proposition in November 2024.

Expected Impact:
HCFCD will use this Term Contact to minimize response times for work order repair projects countywide (Precincts 1, 2, 3 & 4) for Harris County.

Alternative Options:
No renewal will increase the response time to the work repair projects for reducing flooding within the system.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained in...

Click here for full text