Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0193, UPIN 23102MF2Q101
Vendor/Entity Legal Name (if applicable): ECM Construction, LLC
MWBE Contracted Goal (if applicable): 24.07%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with ECM Construction, LLC, in connection with final construction of Fairmont Parkway Improvements, adding 10 calendar days, with a deduction in the amount of $117,427.66, Job No. 25/0193-1, UPIN 23102MF2Q101, Precinct 2, MWBE Contracted Goal: 24.07%, MWBE Current Participation: 100%.
end
Background and Discussion:
The project is in East Harris County, La Porte area, Precinct 2. ECM Construction, LLC was awarded a contract to provide sidewalk and related improvements along Fairmont Parkway from SH 146 to Bayshore Drive.
This change order includes the following items:
PCO-1: Construction Signs. Adding $9,150.00 and 7 days.
PCO-2: Additional Grass, adding $2,344.00 and 3 days.
PCO-3: Final Adjustments, deducting $128,921.66.
Expected Impact:
The project will improve mobility and safety for residents and pedestrians in the vicinity.
Alternative Options:
No other options, the proposed infrastructure is needed to complete the project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all usi...