Legislation Details

File #: 26-5494    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/12/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of an amendment to an agreement with HR Green, Inc. in the amount of $52,068.00 to perform design phase services in connection with the Hufsmith-Kohrville Road Segment 3A project, from approximately 700 feet north of Ezekiel Road to approximately 400 feet north of Boudreaux Road, UPIN 15104M23NP03, Precinct 3.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 15104M23NP03
Vendor/Entity Legal Name (if applicable): HR Green, Inc.

MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with HR Green, Inc. in the amount of $52,068.00 to perform design phase services in connection with the Hufsmith-Kohrville Road Segment 3A project, from approximately 700 feet north of Ezekiel Road to approximately 400 feet north of Boudreaux Road, UPIN 15104M23NP03, Precinct 3.
end

Background and Discussion:
Adkisson Group is developing a site consisting of four (4) warehouse buildings located on Hufsmith-Kohrville Road, across from Kohrville Elementary School at Woodland Shore Drive. The intersection and storm sewer tie ins to the Hufsmith-Kohrville Road Segment 3A are being incorporated into the Harris County capital project to provide a completed intersection at the time of construction complete. To accommodate a proposed development, as part of the roadway project, requiring installation of a fourth leg traffic signal at Woodland Shore Drive, an eastbound left-turn lane at Woodland Shore Drive, three (3) concrete driveways, two (2) storm sewer manholes and storm pipe, installation of a pedestrian signal pole, ADA-compliant curb ramps, pavement markings and other associated roadway improvements.

Expected Impact:
The pr...