Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 19103MF12H02
Vendor/Entity Legal Name (if applicable): Brooks & Sparks, Inc.
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Brooks & Sparks, Inc. in the amount of $103,840.00 for Professional Engineering and related services to construct drainage improvements to the Barwood Subdivision Drainage Improvements - 2018 West, UPIN 19103MF12H02, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end
Background and Discussion:
The project consists of constructing storm sewer drainage improvements to convey runoff from the Barwood West Subdivision to HCFCD Unit E133-00-00. The proposed work includes open-cut installation of new storm sewer facilities, associated street paving, demolition and removal of existing storm sewer segments, traffic control, construction storm water pollution prevention measures, replacement of pavement removed for drainage improvements, pavement markings, and required water and sanitary relocations.
Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. No impact on project schedule or cost anticipated.
Alternative Options:
The County could elect to approve the requested task or choose to re...