Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Barrett Station (Phase 2 Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, with an addition in the amount of $62,146.38, Job No. 23/0337-4, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%, MWBE Participation: 39.03%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0337, UPIN 19102MF14Q01
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 39.03%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Barrett Station (Phase 2 Barrett Settlement & St. Charles Place) Subdivision Drainage Improvements - 2018, with an addition in the amount of $62,146.38, Job No. 23/0337-4, UPIN 19102MF14Q01, Precinct 3, MWBE Contracted Goal: 31%, MWBE Participation: 39.03%.
...end

Background and Discussion:
The project is located in northeast Harris County in the San Jacinto watershed with a small portion in the Cedar Bayou watershed. It is to the south of Barrett Road, east of Crosby-Lynchburg Road, and north of Cottontail Drive. The existing drainage system is roadside ditches. The proposed improvements are to regrade roadside ditches, upsize culverts to increase capacity, and to construct a detention pond for mitigation.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and add new line items on the project for completion of the proposed scope of work.

? The increase of quantities on overrun line items number 36A, 42A, 60A, 63A, 64A, 75, 75A, 76A, 84A, 88A, for an addition in the amount of $323,302.80.
? The decrease in quantities on und...