Title: Request for approval of an interlocal agreement with the City of Pasadena for the removal of a waterline that intersects Flood Control District property, allowing the Flood Control District to improve the stormwater detention facility near HCFCD Project I100-00-00 (Vince Bayou Watershed, Bond ID F-104, Project ID I100-00-00-E001, Agreement No. 2026-40, Precinct 2).
Attachments: 1. 082526 ILA CITY OF PASADENA 2026-40 PCT 2 backup.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): I100-00-00-e001
Vendor/Entity Legal Name (if applicable): City of Pasadena

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with the City of Pasadena for the removal of a waterline that intersects Flood Control District property, allowing the Flood Control District to improve the stormwater detention facility near HCFCD Project I100-00-00 (Vince Bayou Watershed, Bond ID F-104, Project ID I100-00-00-E001, Agreement No. 2026-40, Precinct 2).
end

Background and Discussion:
This interlocal agreement will allow the City of Pasadena to enter the Flood Control District property to remove a waterline that currently intersects Flood Control District property that is proposed to be a future basin, at no cost to the Flood Control District. This project includes utility adjustments and removal. This project occurs in the 2nd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Vince Bayou watershed by clearing utility conflicts out of the way for a proposed detention basin.

Alternative Options:
The alternative to approving this item would be to have the Flood Control District remove the waterline, which would result in potential liability to the City of Pasadena.

County Strategic Plan Goal: 5. Minimize the imp...