Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Z100-00-00-P013
Vendor/Entity Legal Name (if applicable): AECOM Technical Services, Inc.
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable): 20%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of amendment No. 2 to an agreement with AECOM Technical Services, Inc., in the amount of $140,000, to provide additional hydrologic and hydraulic engineering and related services in support of the Flood Control District's model and map maintenance (Project ID Z100-00-00-P013, Agreement No. 2022-193, Countywide, MWBE Contracted Goal: 20%, MWBE Current Participation: 20%).
end
Background and Discussion:
The Flood Control District conducts both Local and Federal reviews of Letter of Map Revisions (LOMRs) and Conditional Letter of Map Revisions (CLOMRs) in Harris County. During the Federal review, the Flood Control District, as LOMR Review partners with FEMA, is only permitted to review cases based on Federal Criteria. The Flood Control District has agreements with the National Flood Insurance Program communities in Harris County that state that those communities will submit LOMR and CLOMR requests to the Flood Control District so that a Local Review can be done before those communities will sign the MT-2 Form 1 that is required for a federal review. This requirement for a Local Review allows the Flood Control District to enforce local modeling and mapping standards that are higher than the federal standards....
Click here for full text