Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 25/0038, UPIN 19104MF12P01
Vendor/Entity Legal Name (if applicable): Cracon Inc
MWBE Contracted Goal (if applicable): 15.00%
MWBE Current Participation (if applicable): 100.00%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Cracon Inc, in connection with final construction of Memorial Hills Subdivision Drainage Improvements - 2018, adding 109 calendar days, with a deduction in the amount of $198,604.64, Job No. 25/0038-1, UPIN 19104MF12P01, Precinct 1, MWBE Contracted Goal: 15.00%, MWBE Current Participation: 100.00%.
end
Background and Discussion:
The project is located in north Harris County in the Cypress Creek watershed, north of FM 1960, south of Cypress Creek, and east of Hardy Toll Road. The project area consists of approximately 84 acres of single-family residential homes. The existing system is a concrete curb and gutter and primarily drains into Briar Creek (K117-00-00). A 72" RCP with associated inlets also aids in draining the western portion of the site. The scope of the project includes constructing a drainage swale and underlying storm sewer behind the commercial tract along FM 1960.
The change in contract includes the following:
The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
* The increase of quantities on overrun line-item numbers 004, 019, 020, 022, 023, 034, 035 ...
Click here for full text