Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Tina Petersen
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Renewal
Project ID (if applicable): 250199
Vendor/Entity Legal Name (if applicable): Sago Solutions LLC (Primary); Ceballos Construction, LLC (Secondary)
MWBE Contracted Goal (if applicable): 29.89%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Sago Solutions LLC (Primary); and Ceballos Construction, LLC (Secondary) for drainage sediment removal and disposal (South) and related items for the Flood Control District for the period of October 1, 2026 - September 30, 2027, at a cost of $1,497,156, and for the County Clerk to execute any applicable bonds to be received (250199), MWBE Contracted Goal: 29.89%.
end
Background and Discussion:
Contract renewal for year 2 (renewal 1) of the Drainage Sediment Removal & Disposal - South contract. These services will provide support for infrastructure maintenance work that will be executed as a result of the passage of the "Maintenance Matters" Proposition in November 2024.
Expected Impact:
HCFCD will use this Term Contact to minimize response times for work order repair projects in south Harris County (Precincts 1, 2, 3, & 4).
Alternative Options:
N/A
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety ...
Click here for full text