Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Tina Petersen
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 230339
Vendor/Entity Legal Name (if applicable): Pape-Dawson Consulting Engineers, LLC
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request that the County Judge execute an amendment to an agreement with Pape-Dawson Consulting Engineers, LLC in the additional amount of $254,541 for additional services for professional engineering and design for expansion of Kluge Stormwater Detention Basin (Part 3) for the Flood Control District (230339), MWBE Contracted Goal: 20%.
end
Background and Discussion:
This Amendment No. 2 will provide for construction phase tasks, including responding to submittals and requests for information, attending monthly progress meetings and bi-weekly update meetings, performing periodic site visits, and completing the necessary pre- and post-construction surveys of the site. The project includes the construction of a wet-bottom detention basin on District-owned property along Little Cypress Creek in an existing stormwater detention basin complex. The project is bounded by Preece Court on the northwest, Wynmar Lane on the northeast, an existing stormwater detention basin on the southeast, and Longwood Trace and Little Cypress Creek on the southwest.
Expected Impact:
The Kluge Stormwater Detention Basin - Phase 3 project will construct 210 acre-feet of detention which will provide flood mitigation and general flood risk reduction benefits to r...