Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 260063
Vendor/Entity Legal Name (if applicable): CFI Mechanical, Inc.
MWBE Contracted Goal (if applicable): 10.4%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of best proposal meeting requirements to CFI Mechanical, Inc. in the amount of $5,360,268 for 1010 Lamar (Annex 48) stairwell pressurization, Heating, Ventilation, and Air Conditioning (HVAC) repair & plumbing renovations for the Office of the County Engineer and for the County Clerk to execute any applicable bonds to be received (260063), MWBE Contracted Goal: 10.4%.
end
Background and Discussion:
The project scope is split into two distinct scope packages:
Stair Pressurization Project: This package includes the Engineering and design to provide a code compliant Stair Pressurization system to the existing building. Two fans will be located on the roof, one for each stair. This includes new vertical risers in fire rated shafts from the roof down to the first floor. This project also includes a new 277/480v-3ph4W. 60KW/75KVA natural gas generator to provide emergency back-up power to the new Stair Pressurization Fans.
Chilled Water Upgrades: This project includes connecting the building to Centrio Energy's underground chilled water distribution system. The scope is to connect to Centrio's provided heat exchangers down in the basement level of the 1111 Main St. garage, install new chilled water pumps on the ...
Click here for full text