Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0127, UPIN 19101MF14N01
Vendor/Entity Legal Name (if applicable): Hassell Construction Group, LLC
MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 337.30%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Hassell Construction Group, LLC, in connection with Hidden Meadow Subdivision Drainage Improvements - 2018, adding 190 calendar days, with an addition in the amount of $97,265.69, Job No. 23/0127-3, UPIN 19101MF14N01, Precinct 1, MWBE Contracted Goal: 27%, MWBE Current Participation: 337.30%.
end
Background and Discussion:
Hidden Meadow is in Northeast Harris County, Texas, Precinct 1. The subdivision is mainly composed of single-family homes and duplexes. The residents have experienced structural flooding during several recent flood events. Approximately 199 homes were reported to have flooded during Hurricane Harvey. The purpose of this project is to reduce flooding for homes within the subdivision. The proposed solution includes upgrading storm sewers and adding a detention pond.
The change in contract includes the following:
The line items have been adjusted to reconcile overrun quantities and to include new line items needed to complete the proposed scope of work.
* The increase of quantities for line items 27, 28, 29, 45, 79 for an addition in the amount of $49,397.00 and zero (0) days.
* Added new line item 107 - Bore for W...
Click here for full text