Primary Department: Commissioner, Precinct 2
Primary Department Head/Elected Official: Adrian Garcia, Commissioner
Managing Department: Commissioner, Precinct 2
Managing Department Head/Elected Official: Adrian Garcia, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Hardy Community Center HVAC Replacement
Project ID (if applicable): 100001000001458
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $1,056,700
Total Estimated Project Cost: $1,380,700
Request Summary:
title
Request for approval of a Final Investment Memo for the Hardy Community Center HVAC Replacement, for an incremental amount of $1,056,700 for a total authorization of $1,380,700, and incremental commercial paper funding in the amount of $1,060,000 for a total allocation of $1,385,000.
end
Project Description:
The requested funds are for the replacement of the Heating, Ventilation, and Air Conditioning (HVAC) System at the Hardy Community Center serving the Aldine Area. The existing facility is located at 11901 W. Hardy Road, Houston, TX 77076, on a 521,000 square foot tract of land owned by the County of Harris.
The Hardy Community Center project will include the complete demolition of all existing HVAC systems and associated components. The new replacement system will be more efficient, resilient, and sustainable. Additionally, improvements include HVAC automated controls and upgrading the building's envelope (physical barrier between the conditioned and unconditioned environment of the building).
Anticipated Project Expenditures and Timeline:
Scope of Work
Estimated...
Click here for full text