Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0019, UPIN 22103MF2E401
Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): 31.81%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with GLM Contracting, Inc., in connection with final construction of On-Call - Construction - General Civil, Precinct 3 - 2021, with no change in the amount, Job No. 22/0019-2, UPIN 22103MF2E401, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 31.81%.
end
Background and Discussion:
Project includes general civil services to areas throughout Precinct 3. The change in contract is to include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. The new bid item is only to establish the unit price and there is no change to the contract amount. The terms of services in connection with the purchase order will be closed at the request of the Precinct.
Change includes:
PCO-62; Work at 4219 Krenek - (LS) lump sum, - $22,800.00
PCO-63; Work at Dog Park at 1502 Mortiz - (LS) lump sum, - $7,000.00
PCO-64; 1502 Mortiz Drive - 4" PVC pipe - (LS) lump sum, - $11,520.00
PCO-65; Walls at Wirt Road - (LS) lump sum, - $6,822.00
Expected Impact:
Change allows Contractor to get compensated for the actual work completed on the project and allows unused funds to be returned to the ...