Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): Z100-00-00-Y102
Vendor/Entity Legal Name (if applicable): Board of Regents of the University of Oklahoma
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to negotiate an agreement with Board of Regents of the University of Oklahoma for enhancement of the existing Gauge Adjusted Radar Rainfall Multi-Radar Multi-Sensor product to improve accuracy, operational capabilities, and support improved flood forecasting in Harris County (Countywide).
end
Background and Discussion:
This request for authorization to negotiation is for an agreement that will provide an enhanced Gauge Adjusted Radar Rainfall (GARR) Multi-Radar Multi-Sensor (MRMS) product that offers additional resources and product development for improved flood forecasting in Harris County. This project is a continuation and expansion of the initial Cooperative Research and Development Agreement (CRADA) between the Harris County Flood Control District (HCFCD) and the National Severe Storms Laboratory (NSSL), which established a limited Multi-Radar Multi-Sensor (MRMS) domain over Harris County using HCFCD's dense rain gauge network.
Expected Impact:
The future agreement will enhance the accuracy and operational capability of the GARR MRMS product by integrating verification tools, cloud-based processing, and sub-hourly nowcasting capabilities. These improvements will lead to better spat...