Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Tolunay-Wong Engineers, Inc.
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an agreement with Tolunay-Wong Engineers, Inc., in the amount of $112,500, to provide materials engineering and testing services in support of maintenance construction projects countywide (Agreement No. 2025-27, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible).
end
Background and Discussion:
This is a request to authorize negotiation for an agreement that will provide materials engineering and testing services for construction projects throughout the County. Major emphasis of this repair work will be earthwork, including but not limited to erosion repair, slope failure repair, removal and disposal of sediment accumulations, granular fill and riprap installation, pipe removal and replacement, headwall and wingwall removal and replacement, concrete channel lining removal and replacement, concrete low-flow removal and replacement, outfall structure removal and replacement and related items. Construction materials testing will provide quality control and assurance to ensure that flood risk reduction projects are constructed properly.
Expected Impact:
Materials engineering and testing services under this agreement will provide essential quality control and assurance, ensuring that soils and construction materials me...
Click here for full text