File #: 25-3490    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action:
Title: Request for approval to execute an agreement with Raba Kistner, Inc. for construction materials testing services for the replacement of pavement terminal anchor sections on bridges of Hardy Toll Road in the amount of $330,000.00 (Precincts 1, 2, and 3, MWBE Contracted Goal: 19.6%).
Attachments: 1. 25-3490 - RABA_KISTNER_-_CMT_Agreement_(Heavy_Maintenance)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Raba Kistner, Inc.

MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Raba Kistner, Inc. for construction materials testing services for the replacement of pavement terminal anchor sections on bridges of Hardy Toll Road in the amount of $330,000.00 (Precincts 1, 2, and 3, MWBE Contracted Goal: 19.6%).
end

Background and Discussion:
On March 27, 2025, Commissioners Court approved negotiations with Raba Kistner, Inc. for construction materials testing. The construction materials testing services will provide material testing during construction of structural elements that were identified to undergo replacement.

Expected Impact:
Improved roadway conditions and extension of life expectancy for bridges.

Alternative Options:
No other recommended option for this identified need.

County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A

Additional notes related to the Strategic Plan: N/A

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
3/27/2025
203
Request to Negotiate

Location: