Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24035MF38F01
Vendor/Entity Legal Name (if applicable): Kirksey Architecture, Inc.
MWBE Contracted Goal (if applicable): 18.3 %
MWBE Current Participation (if applicable): 0 %
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Kirksey Architecture, Inc., in the amount of $916,060.00 for Professional Services to Prepare Plans Specifications & Cost Estimate documents in connection with demolition and site grading for the Family Law Center building located at 1115 Congress St, Houston, TX 77002 - Demolition - UPIN 24035MF38F01, Precinct 1, MWBE Contracted Goal: 18.3%.
end
Background and Discussion:
The Office of the County Engineer has requested the Prime - Kirksey Architecture to provide design phase documents for the demolition of the Family Law Center Building located at 1115 Congress St, Houston, TX 77002. The Family Law Building was built in 1968, 7-story high rise courthouse building is approximately 106,200 SF. The total cost of the project was estimated to be $10,220,000.
Expected Impact:
The demolition project will allow for future use in Precinct 1.
Alternative Options:
There are no viable alternatives.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
...
Click here for full text