Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN - 23103MF2Q701
Vendor/Entity Legal Name (if applicable): HR Green, Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by HR Green Inc., for Hufsmith-Kohrville Road Segment 3B - from 400' north of Boudreaux Road to 600' north of Holderrieth Road - 2015, UPIN 23103MF2Q701, Precinct 3.
end
Background and Discussion:
This project consists of upgrading Hufsmith-Kohrville Road to a standard four (4) lane concrete boulevard in 100-foot ROW with a 32-foot raised median and underground storm sewer system for the updated limits from 400' north of Boudreaux Road to 600' north of Holderrieth Road. The project includes a new bridge across Willow Creek M100 channel and sidewalks.
Expected Impact:
The project will improve the north-south vehicular mobility for the local community. The proposed bridge will expand the entire channel, and the proposed elevation will reduce the bridge flooding.
Alternative Options:
Without this project, this road segment will continue operating under the current conditions without the improved 4 lane configuration.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation netwo...
Click here for full text