Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 24208MF3F901
Vendor/Entity Legal Name (if applicable): Midtown Engineers, LLC
MWBE Contracted Goal (if applicable): 3.77%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Midtown Engineers, LLC in the amount of $840,313.00 for Professional Engineering and related services in connection with Subdivision Improvements - Highlands - 2024, UPIN 24208MF3F901, Precinct 3, MWBE Contracted Goal: 3.77%.
end
Background and Discussion:
Precinct 3 is requesting the Office of the County Engineer to enter into an agreement for professional engineering services to remove the roadside ditches, and construct five-foot-wide sidewalks by installing a storm sewer system for subdivisions in the Highlands area. The study phase will cover the entire area, with Phase One focusing on design and construction. The Highlands area is bounded by West Canal Road to the north, Crosby Lynchburg Road to the east, Harris Road to the south and the San Jacinto River to the west.
Expected Impact:
The project will ensure the subdivisions in the Highlands community are maintainable and functional.
Alternative Options:
Without this project, the roads cannot be maintained properly. The goal is to enhance safety, pedestrian flow, and drainage, as requested by Precinct3.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and ...