File #: 25-3436    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with First Class Units, Inc. in connection with the New Restroom - A.D. Dyess Park - 2023, adding 53 calendar days, with an addition in the amount of $22,000.00, Job No. 24/0197-1, UPIN 24103MF30N01, Precinct 3, MWBE Contracted Goal: 5.824%, MWBE Current Participation: 6%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E.

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 24/0197, UPIN 24103MF30N01
Vendor/Entity Legal Name (if applicable): First Class Units Inc.

MWBE Contracted Goal (if applicable): 5.824%
MWBE Current Participation (if applicable): 6%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with First Class Units, Inc. in connection with the New Restroom - A.D. Dyess Park - 2023, adding 53 calendar days, with an addition in the amount of $22,000.00, Job No. 24/0197-1, UPIN 24103MF30N01, Precinct 3, MWBE Contracted Goal: 5.824%, MWBE Current Participation: 6%.
end

Background and Discussion:
This project is located at A.D. Dyess Park, 16822 Kitzman Rd Houston, TX 77429. This project is aimed at replacing an antiquated restroom with a prefabricated restroom with HVAC and all appurtenances per design documents, utilities connection and SWPPP incidental. This change in contract entails a change in roof texture for the prefabricated restroom, 32 LF of 12" RCP as SWPPP item omitted on the bid tabulation and a no cost time extension of 53 calendar days due to prefab building long lead item. The NTP for this project was issued as a whole, a partial NTP was preferable in this case to enable procuration of prefab building.

Expected Impact:
Changes allow the completion of the project in accordance with the original intent of the project.

Alternative Options:
Should we not move forward with this change order, the p...

Click here for full text