File #: 25-3429    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with DVL Enterprises LLC, in connection with final construction of Humble Westfield Road from West Hardy Road to FM 1960 - 2020, adding 505 calendar days, with a deduction in the amount of $376,941.34, Job No. 22/0170-1, UPIN 21101MF1NU01, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 26.28%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0170, UPIN 21101MF1NU01
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 26.28%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises LLC, in connection with final construction of Humble Westfield Road from West Hardy Road to FM 1960 - 2020, adding 505 calendar days, with a deduction in the amount of $376,941.34, Job No. 22/0170-1, UPIN 21101MF1NU01, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 26.28%.
end

Background and Discussion:
This project is a reconstruction of Humble Westfield adding shoulders and repairing any failing asphaltic base materials. The project was constructed per the plans and at the completion of the work the cores taken per Harris County specification failed to meet the minimum requirements. The contractor disputed the results and consulted an attorney. The project was handed over to the County Attorney's Office and the project was on pause until a resolution was reached. The resolution was agreed to between both parties and resulted in a contract deduction of payment. The remaining work was completed, and no Liquidated Damages were charged to the contractor. This final change order is per the agreement to reduce payment and extend the contract to remove any Liquidated Damages.

Expected Impact:
This final chan...