Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No: 23/0286, UPIN 19101MF0XZ01
Vendor/Entity Legal Name (if applicable): John Reed and Company, LLC
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with John Reed and Company, LLC in connection with Brays Bayou Pedestrian/Bike Bridge near Stella Link/Glen Arbor, adding 60 calendar days, with an addition in the amount of $70,203.97, Job No. 23/0286-4, UPIN 19101MF0XZ01, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end
Background and Discussion:
The project is to construct a pedestrian bridge over Brays Bayou to connect the pedestrian facilities from North Braeswood Boulevard to South Braeswood Boulevard, east of Stella Link Road. The bridge has 3-spans with 226 feet length and approximate 400 feet ramps.
Expected Impact:
Provide safe pedestrian and cyclist crossing over Brays Bayou between North Braeswood Boulevard to South Braeswood Boulevard.
Alternative Options:
N/A
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infrastructure...
Click here for full text