File #: 25-3426    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with The Brandt Companies, LLC, in connection with Facilities - East Harris County Activities Center - HVAC - Precinct 2, with an addition in the amount of $14,600, Job No. 23/0480-01, UPIN 23102MF2TD01, Precinct 2, MWBE Contracted Goal: 7%, MWBE Current Participation: 29.06%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 230480
Vendor/Entity Legal Name (if applicable): The Brandt Companies, LLC

MWBE Contracted Goal (if applicable): 7%
MWBE Current Participation (if applicable): 29.06%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with The Brandt Companies, LLC, in connection with Facilities - East Harris County Activities Center - HVAC - Precinct 2, with an addition in the amount of $14,600, Job No. 23/0480-01, UPIN 23102MF2TD01, Precinct 2, MWBE Contracted Goal: 7%, MWBE Current Participation: 29.06%.
end

Background and Discussion:
Project includes replacing existing HVAC system at Precinct 2 - East Harris County Activity Center (EHCAC) with new?HVAC system including 5 air handler units (AHUs), 1 Outside Air Handling unit (OAHU) and 1 new electric?hot water heater.? EHCAC was built in 1992 and utilizes the original AHUs which have exceeded their life span. This project was initiated to address poor efficiency, excess humidity, and heat buildup. The proposed air handlers will address all these issues and reduce the electrical consumption.

The change order addresses extending current concrete pads for increased structural stability of new AHUs. The change order cost is $14,600.

Expected Impact:
The change allows the AHUs to have proper structural stability to prevent any structural integrity loss to the entire building.


Alternative Options:
Continue with the project in accordance with the original sc...

Click here for full text