Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 25101MF3N301
Vendor/Entity Legal Name (if applicable): Infrastructure Engineering, Inc.
MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Infrastructure Engineering Inc., in the amount of $1,318,123.00 for Professional Engineering Services to provide roadway, storm sewer and sidewalk improvements along Hafer Road from FM 1960 to Skywood Drive, UPIN 25101MF3N301, Precinct 1, MWBE Contracted Goal: 19.6%.
end
Background and Discussion:
The project is to design the reconstruction of Hafer Road, approximately one mile, from FM 1960 to Skywood Drive. The reconstruction includes a new concrete pavement with storm sewer and detention basin, sidewalk, and a traffic signal.
Expected Impact:
The proposed improvement will provide a safe condition for the vehicular and pedestrian traffic with better drainage system requiring less maintenance.
Alternative Options:
No Alternative options. If not approved, project will be delayed or could get canceled.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infr...
Click here for full text