Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S Ramsey, P.E.
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 23103MF2PH01
Vendor/Entity Legal Name (if applicable): Harris County Water Control and Improvement District No. 110
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Water Control and Improvement District No. 110 for design, construction and maintenance responsibilities for utilizing the Harris County Water Control and Improvement District No. 110 detention basin, UPIN 23103MF2PH01, Precinct 3.
end
Background and Discussion:
The Holzwarth Road project is in NW Harris County, classified as a major thoroughfare with high volumes of traffic. A significant number of accidents have been reported for portions of this corridor. The interlocal is a joint agreement to utilize the existing WCID 110 basin for detention needs.
Expected Impact:
The intent of this agreement is to utilize the WCID 110 existing detention basin and expand it to meet the needs of the Holzwarth Road project. The precinct will maintain the pump station and the detention basin.
Alternative Options:
The alternative is to not utilize Harris County Water Control and Improvement District No. 110's basin and identify another basin location.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
In...