File #: 25-2664    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action:
Title: Request for approval of a change in contract with Solid Bridge Construction, LLC, in connection with Detention Basin Enhancement Program - Cypress - 2021, with an addition in the amount of $5,200.00, Job No. 23/0463-1, UPIN 21103N306430001, Precinct 3, MWBE Contracted Goal: 24%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0463, UPIN 21103N306430001
Vendor/Entity Legal Name (if applicable): Solid Bridge Construction, LLC

MWBE Contracted Goal (if applicable): 24%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Solid Bridge Construction, LLC, in connection with Detention Basin Enhancement Program - Cypress - 2021, with an addition in the amount of $5,200.00, Job No. 23/0463-1, UPIN 21103N306430001, Precinct 3, MWBE Contracted Goal: 24%.
end

Background and Discussion:
The (K500-01-00 Detention Basin Expansion) project site consists of stormwater detention basin located northwest of Harris County in Cypress Creek Watershed, discharging into Harris County Flood Control Channel K100-01-00 Cypress Creek.

The change involves adding a missing item to the contract, increasing the current contract value by $5,200.00 to ensure the project is completed as originally intended.

Item to be added:
(PCO 1) - Removal and Disposal of 48" HDEP Pipe, Cost: $5,200.00, Additional Days: 0 Days
80 LF x $65/LF = $5,200.00

Expected Impact:
The overall objective for this project is to provide stormwater detention storage to mitigate drainage improvements to the Dowdell Woods & Cypress Creek Estates Subdivisions that drain to Cypress Creek. This change enables the addition of a new item to the contract, ensuring the project aligns with the original intent and com...

Click here for full text