Title: Request for approval of a change in contract with Bear Services, LP, in connection with Sidewalk - Holland Avenue - 2021, adding 128 days, with no change in the amount, Job No. 21/0365-1, UPIN 22102MF2DC01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 23.35%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0365, UPIN 22102MF2DC01
Vendor/Entity Legal Name (if applicable): Bear Services, LP

MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 23.35%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Bear Services, LP, in connection with Sidewalk - Holland Avenue - 2021, adding 128 days, with no change in the amount, Job No. 21/0365-1, UPIN 22102MF2DC01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 23.35%.
end

Background and Discussion:
The construction project along Holland Avenue, extending from Clint Drive to 18th Street, involves the installation of sidewalks and driveways to enhance pedestrian accessibility and safety. This initiative aims to provide a continuous and ADA-compliant pedestrian pathway, improving connectivity for residents and facilitating safer routes for pedestrians.
The project faced several challenges that required design modifications and adjustments, resulting in a cumulative delay of 128 days without additional costs.
1. Field Condition Adjustments (PCOs 1, 3, 4, 6, 7)
Adjustments were required due to unexpected field conditions, such as driveway slope corrections, drainage improvements, retaining wall installations, and trench drains to maintain compliance and stability.
Total Schedule Impact: 47 days.
2. Design Plan Revisions (PCOs 2, 5, 8, 10, 12)
Modifications to the original desig...

Click here for full text