Title: Request for approval of a change in contract with Cracon, Inc., in connection with Sidewalk and Access Management - Ella Blvd from Richey Rd to FM 1960, adding 85 calendar days, with an addition in the amount of $77,129.24, Job No. 22/0190-1, UPIN 21208MF21401, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 100%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0190, UPIN 21208MF21401
Vendor/Entity Legal Name (if applicable): Cracon, Inc.

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Cracon, Inc., in connection with Sidewalk and Access Management - Ella Blvd from Richey Rd to FM 1960, adding 85 calendar days, with an addition in the amount of $77,129.24, Job No. 22/0190-1, UPIN 21208MF21401, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 100%.
end

Background and Discussion:
Project includes new sidewalks along Ella Boulevard from North of Richey Road to FM 1960, access management, rebuild Ella Boulevard traffic signals at Southridge and at North Forest, new traffic signal at Butterfield Road, and new bus stop landings.

This change in contract includes:
? PCO-1, Additional ramps to tie in existing sidewalk, various locations adding $3,500 with 10 days.
? PCO-2, The addition of 2 traffic signal at Butter Field adding $22,457 with 30 days.
? PCO-3, The relocation of a conflicting existing force main along the Right-of-Way adding $51,172.24 with 45days.


Expected Impact:
Changes will allow for the project to be constructed per the plans.

Alternative Options:
Revise original scope of the project.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintai...