File #: 25-2640    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action:
Title: Request for approval of a change in contract with Times Construction, Inc., in connection with final construction of Boyce Dorian and Lincoln Park Improvements Plan - 2019, adding 386 calendar days, with a deduction in the amount of $87,553.92, Job No. 23/0139-1, UPIN 20101MF1G901, Precinct 1, MWBE Contracted Goal: 21%, MWBE Current Participation: 44.09%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0139, UPIN 20101MF1G901
Vendor/Entity Legal Name (if applicable): Times Construction, Inc.

MWBE Contracted Goal (if applicable): 21%
MWBE Current Participation (if applicable): 44.09%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Times Construction, Inc., in connection with final construction of Boyce Dorian and Lincoln Park Improvements Plan - 2019, adding 386 calendar days, with a deduction in the amount of $87,553.92, Job No. 23/0139-1, UPIN 20101MF1G901, Precinct 1, MWBE Contracted Goal: 21%, MWBE Current Participation: 44.09%.
end

Background and Discussion:
This project is a park improvement project located on the north side of Houston in Precinct 1. The proposed project will make improvements to Lincoln Park. These improvements include a new wood deck, new walking trail, landscape items and improvements to park entry area.

This change order includes payment for relocating a tree and irrigation. Days for working around tree roots in order to protect large mature tree. Days for stopping work to accommodate a city of Houston event and adding sod. Additional days needed for down time while waiting for engineer of record to review and redesign proposed deck. Payment for requested revision to park signs place by contractor and payment to repair storm damage to new signs.

Expected Impact:
Changes will allow for the project to be constructed per the original inte...