Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0341, UPIN 23035MF2NM01
Vendor/Entity Legal Name (if applicable): Statewide Traffic Signal Co.
MWBE Contracted Goal (if applicable): 8.60%
MWBE Current Participation (if applicable): 9.69%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Statewide Traffic Signal Co. in connection with final construction of Traffic Signal - Cypress North Houston Road at Barker Trace Drive - 2022, adding 89 calendar days, with an addition in the amount of $16,697.11, Job No. 23/0341-1, UPIN 23035MF2NM01, Precinct 3, MWBE Contracted Goal: 8.60%, MWBE Current Participation: 9.69%.
end
Background and Discussion:
Project involves constructing new Traffic signal comprising of mast arms, pedestrian improvements including upgrades to ADA ramps, striping, signage improvements and loop detectors.
Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.
- Final Adjustments $16,697.11,
Change also include added 89 calendar days as follow.
- PCO - 1 Additional 33 days due to AT&T pedestal and pull box conflict with proposed controller cabinet foundation.
- PCO - 2 Additional 3 days due to inclement weather (Hurricane Beryl)
- PCO - 3 Additional 18 days due to CPE transformer installation.
- PCO - 4 Additional 5 days to relocate push buttons and add a retaining wall.
- PCO - 6 Additional 30 days due to waiting on Centerpoint power.
...
Click here for full text