File #: 25-2630    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action:
Title: Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Water Distribution and Sanitary Sewer System Construction - West Nelda - 2021, with a deduction in the amount of $214,179.40, Job No. 23/0096-1, UPIN 21289MF1Z601, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100.29%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0096, UPIN 21289MF1Z601
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC

MWBE Contracted Goal (if applicable): 24%
MWBE Current Participation (if applicable): 100.29%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Water Distribution and Sanitary Sewer System Construction - West Nelda - 2021, with a deduction in the amount of $214,179.40, Job No. 23/0096-1, UPIN 21289MF1Z601, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100.29%.
end

Background and Discussion:
The proposed construction of West Nelda & West Mierianne Street Water Distribution and Sanitary Sewer Systems Project consists of construction of water distribution line, and construction of sanitary sewer line, decommissioning of water wells for existing lots after installation of water lines.

The project had an initial construction budget of $719,137.80 to connect potable water and sewer lines to 38 residences. Upon bidding and awarding the project, several residents chose not to have water and/or sewer connections. 22 of 38 water connections were made, 19 of 38 sewer connections were made. This is the primary reason of the budget's reduction. There are some offsets to that reduction with unforeseen field conditions, scope adjustments, and requirements to comply with regulatory standar...

Click here for full text