Title: Request for approval of an award on the basis of low bid to iCON GC, LLC in the amount of $15,635,000 for drainage improvements in the Parkway (Mobile Homes) Subdivision (2018) for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250039), MWBE Contracted Goal: 29.78%.
Primary Department: Purchasing
Primary Department Head/Elected Official: Paige McInnis

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 250039
Vendor/Entity Legal Name (if applicable): iCON GC, LLC

MWBE Contracted Goal (if applicable): 29.78%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to iCON GC, LLC in the amount of $15,635,000 for drainage improvements in the Parkway (Mobile Homes) Subdivision (2018) for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250039), MWBE Contracted Goal: 29.78%.
end

Background and Discussion:
The County advertised Parkway (Mobile Homes) Subdivision Drainage Improvements project for bid and now seeks to award the construction contract based on the lowest and responsive bidder. The Parkway (Mobile Homes) Subdivision Drainage Improvements project site consists of subdivision drainage improvements and stormwater detention basin located south of the intersection of Park Trail Drive and Tidwell Road, discharging into Harris County Flood Control District Channel Unit No. P122-00-00. Major work activities include off-site disposal of about 138,000 cubic yards of excavation and a wet bottom stormwater detention basin. The construction of the stormwater detention basin will consist of clearing and grubbing of piezometers, site grading, and maintenance access paths according to Plans.

Expected Impact:
This action will allow iCON GC, LLC to proceed with the construction of the project.

Alternative Options:
If no action is taken, t...