File #: 25-2147    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/25/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Evergreen Villas Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $30,328.16, Job No. 23/0138-4, UPIN 19101MF14M01, Precinct 1, MWBE Contracted Goal: 27%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0138, UPIN 19101MF14M01
Vendor/Entity Legal Name (if applicable): Blazey Construction Services, LLC

MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Evergreen Villas Subdivision Drainage Improvements - 2018, adding 4 calendar days, with an addition in the amount of $30,328.16, Job No. 23/0138-4, UPIN 19101MF14M01, Precinct 1, MWBE Contracted Goal: 27%, MWBE Current Participation: 100%.
end

Background and Discussion:
Evergreen Villas is in Northeast Harris County, Texas, Precinct 1. The subdivision is mainly composed of single-family homes. The residents have experienced structural flooding during several recent flood events. Approximately 37 homes were reported to have flooded during Hurricane Harvey. The purpose of this project is to reduce flooding for homes. The proposed solution includes upgrading storm sewers and adding a detention pond. This contract includes construction services for the construction phase.

The change in contract includes the following:

Quantity Adjustment: The line items are adjusted to reconcile overrun quantities on the project for completion of the proposed scope of work.

* The increase of quantities on line item number 053 for an addition in the amount of $13,881.95.


New line items:

* Added ...

Click here for full text