Title: Request for approval to execute an interlocal agreement with the Texas Department of Transportation for a Local On-System Improvement Project of roadway improvements including extending the existing two-lane road to four lanes, drainage improvements, concrete pavement widening, sidewalk installation, pavement markings, signage and restriping in Tomball, UPIN 15104M23NP03, Precinct 3.
Sponsors: Mony Hossain
Attachments: 1. 25-2139-Partnership-UPIN 15104M23NP03-Texas Dept. Of Transportation-LOSA Tomball-P3.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 15104M23NP03
Vendor/Entity Legal Name (if applicable): Texas Department of Transportation

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with the Texas Department of Transportation for a Local On-System Improvement Project of roadway improvements including extending the existing two-lane road to four lanes, drainage improvements, concrete pavement widening, sidewalk installation, pavement markings, signage and restriping in Tomball, UPIN 15104M23NP03, Precinct 3.
end

Background and Discussion:
The Project consists of the design and construction of roadway improvements along SH 99 underpass at Hufsmith Kohrville Road. Roadway improvements include extending the existing two-lane road to four lanes, drainage improvements, concrete pavement widening, sidewalk installation, pavement markings, signage and restriping in Tomball, Tomball, Precinct 3.

Expected Impact:
The approval of this Local On-System Agreement will allow for the County to construct the improvements of the project.

Alternative Options:
Not approving this Local On-System Agreement, which will prohibit construction of the project improvements. Not being able to construct the improvements will result in maintaining the current traffic operations and pedestrian accessibility conditions of the intersection.

County Strategic...