File #: 25-2105    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/25/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval of a change in contract with Texas Wall & Landscape, LLC in connection with construction of Townsen Park-n-Ride Multimodal Connector, adding 9 calendar days, with an addition in the amount of $22,973.96, Job No. 23/0268-2, UPIN 14104MF0AV01, Precinct 3, MWBE Contracted Goal: 3%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0268, UPIN 14104MF0AV01
Vendor/Entity Legal Name (if applicable): Texas Wall & Landscape, LLC

MWBE Contracted Goal (if applicable): 3%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Wall & Landscape, LLC in connection with construction of Townsen Park-n-Ride Multimodal Connector, adding 9 calendar days, with an addition in the amount of $22,973.96, Job No. 23/0268-2, UPIN 14104MF0AV01, Precinct 3, MWBE Contracted Goal: 3%.
end

Background and Discussion:
The project consists of construction of multimodal connector trail that will connect Spring Creek Greenway Hike and Bike trail to Townsen Park and Ride as well as to the historical US 59 bridge crossing the San Jacinto River in Harris County Precinct 3

This change in contracts includes:
* Change includes cost and time for installation of seal slab underneath the channel lining ($17,325.00 - 5 days).
* Cost of adding bid item for trench safety system. ($4220.00 - 3 days).
* Cost and time for removal of additional abandoned Reinforced concrete pipe and Manhole in conflict with proposed work. ($1,428.96 - 1 day).

Expected Impact:
Change allows to install seal slab underneath the channel lining per TXDOT detail, allows to add trench safety system to the project per standard detail and remove additional abandoned structure which conflicted with proposed work.

Alternative Options:
to re design the work which would be costly.

County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/...