Harris County Logo
File #: 25-2023    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/18/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalks and Undercrossing Project - Fry, adding 31 calendar days, with an addition in the amount of $97,696.60, Job No. 23/0117-3, UPIN 20103N302902, Precinct 4, MWBE Contracted Goal: 33%, MWBE Current Participation: 16.87%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0117, UPIN 20103N302902
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWBE Contracted Goal (if applicable): 33%
MWBE Current Participation (if applicable): 16.87%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalks and Undercrossing Project - Fry, adding 31 calendar days, with an addition in the amount of $97,696.60, Job No. 23/0117-3, UPIN 20103N302902, Precinct 4, MWBE Contracted Goal: 33%, MWBE Current Participation: 16.87%.
end

Background and Discussion:
The project includes the construction of concrete sidewalk with ADA ramps on Fry Road from Park Row Road to Saums Road. This project was completed to unsure reliable and safe routes of transportation to residents of the Harris County. The project was overseen by Harris County Office of the County Engineer - Construction Programs Division team.

This final change order is for an addition of the final adjustment in the amount of $97,696.60. This change order includes quantity adjustments of existing items for final values. Final Adjustment is the reconciliation of actual quantities used in construction against the bid quantities.

(PCO #3) Day Extension: 31 Days
(PCO #4) Final Adjustment: $97,696.60



Expected Impact:
The change allows the addition of bid item quantities in the contract and...

Click here for full text