File #: 24-5598    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 9/4/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Transmittal by the Flood Control District of a preliminary engineering report by Kuo & Associates, LLC dated May 29, 2024, and titled Preliminary Engineering Report for Red Bluff Detention Basin. (Armand Bayou Watershed, Bond ID F-99, Project ID B500-04-00-E004, Precinct 2).
Attachments: 1. 091924 TRANSMITTAL PER B500-04-00-E004 PCT 2 backup.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): B500-04-00-E004
Vendor/Entity Legal Name (if applicable): Kuo & Associates, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a preliminary engineering report by Kuo & Associates, LLC dated May 29, 2024, and titled Preliminary Engineering Report for Red Bluff Detention Basin. (Armand Bayou Watershed, Bond ID F-99, Project ID B500-04-00-E004, Precinct 2).
end

Background and Discussion:
This Preliminary Engineering Report (PER) analyzed configurations of the proposed expansion of the Red Bluff Stormwater Detention Basin and developed a recommended alternative that would optimize and expand the existing dry bottom detention basin.

Expected Impact:
The acceptance of this preliminary engineering report will allow the Flood Control District to move towards detailed design of the project to reduce flood risks and strengthen resiliency in the Armand Bayou watershed.

Alternative Options:
The alternative to approving this item would be not approving this Preliminary Engineering Report, which would result in the Flood Control District not proceeding with the final design of this project and flood risk would remain the same in the area.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any): N/A
Date
Agenda Item #
Action Taken




Location: Red Bluff and Spencer Highway
Address (if applicable):
Precinct(s): Precinct 2

Fiscal and Personnel Summary
Service Name
N/A


Current Fiscal Year Cost
A...