Department: District Clerk
Department Head: Marilyn Burgess
Regular or Supplemental RCA: Supplemental RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: District Clerk Restroom Addition
Project ID (if applicable): TBD
Vendor Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Managing Entity: Office of County Engineer
Incremental Authorization Requested: $284,500
Total Estimated Project Cost: $284,500
Request Summary:
title
Request by the District Clerk for approval of a Final Investment Memo for the District Clerk Restroom Addition project for an initial amount of $284,500.
end
Project Description:
The District Clerk's Office (DCO) is requesting the renovation of the 1st floor restrooms at 5900 Canal to address critical deficiencies in the existing facilities. The proposed renovation will introduce modern, efficient restrooms designed to accommodate the current and anticipated increase in staff levels. As the number of employees and officers at the facility continues to grow, these upgraded restrooms will ensure that all personnel have access to adequate and sanitary facilities, significantly enhancing comfort and operational efficiency.
Project Scope:
The detailed scope of work for the 1st floor restroom renovation at 5900 Canal is listed in the table below. The proposed costs of this project include a $6,300 consultant fee from Gordian. In addition, a $26,000 contingency cost for unforeseen issues is included for a total of $284,500. Please see an overview of the scope of work below:
* Site Preparation: Includes site clearing, grading, and excavation as necessary for the renovation.
* Structural Work: Encompasses concrete removal and replacement, masonry work for new walls and partitions, and repair of existing structural elements.
* Finishes and I...