File #: 24-5806    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/6/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a change in contract with Ballast Point Construction, Inc., in connection with Trail - Fairmont Parkway from HCFCD B100 to Red Bluff Drive - 2021, with an addition in the amount of $20,356.90, Job No. 23/0224-4, UPIN 22102MF2FC01, Precinct 2, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 22.41%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0224, UPIN 22102MF2FC01
Vendor/Entity Legal Name (if applicable): Ballast Point Construction, Inc.

MWDBE Contracted Goal (if applicable): 30%
MWDBE Current Participation (if applicable): 22.41%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Ballast Point Construction, Inc., in connection with Trail - Fairmont Parkway from HCFCD B100 to Red Bluff Drive - 2021, with an addition in the amount of $20,356.90, Job No. 23/0224-4, UPIN 22102MF2FC01, Precinct 2, MWDBE Contracted Goal: 30%, MWDBE Current Participation: 22.41%.
end

Background and Discussion:
Construction of 10-foot-wide trail along Fairmont Parkway from Armand Bayou Hike and Bike Trailhead to Red Bluff Drive, with a pedestrian bridge at Armand Bayou (B100-00-00). Proposed trail includes upgraded audio pedestrian signals, crosswalks, and ramps at signalized intersections at Center Street and Red Bluff Drive.

Bid Item #023 conflicts with the construction plans by specifying a 6-inch HES thickness for the driveway while the plans clearly indicate a required 10-inch concrete slab. As confirmed by the engineer, the discrepancy is due to an error in the bid item and does not reflect the project design. This change will add additional amount of $20,356.90 and no additional days.

Expected Impact:
Increase the total cost for the contract.

Alternative Options:
No action will result in substandard construction.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Acti...

Click here for full text