File #: 24-5687    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/5/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a change in contract with Reytec Construction Resources, Inc., in connection with Oak Glen Place Subdivision Drainage Improvements - 2018, adding six calendar days, with an addition in the amount of $28,639.96, Job No. 23/0028-3, UPIN 19101MF13601, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 26.07%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 19101MF13601 - Job No. 23/0028
Vendor/Entity Legal Name (if applicable): Reytec Construction Resources, Inc.

MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 26.07%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reytec Construction Resources, Inc., in connection with Oak Glen Place Subdivision Drainage Improvements - 2018, adding six calendar days, with an addition in the amount of $28,639.96, Job No. 23/0028-3, UPIN 19101MF13601, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 26.07%.
end

Background and Discussion:
The location of the work is in the Oak Glen Place (East) subdivision in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, driveways paving, widening, and regrading of existing roadside ditches, and construction of a new detention pond.

The Change in contract is needed to reconcile the overrunning items with the underrunning items and adding a new line item to the contract. Below is a summary of changes:

* Added a new line item #146 - swapping asphalt driveways with 6" reinforced concrete driveways and item #151 - replacement of existing concrete walkways for an additional cost in the amount of $325,523.00 and 6 calendar days.

* Quantity Adjustment: The items are adjusted to reconcile overrun and underrun quantities on the project. The increase of quantities removing asphalt driveways, crushed aggregate driveways, filter fabric barrier, (items 4, 18 and 117) for an addition in the amount of $23,304.96.

* The decrease of quantities on underrun line item#20 for a deduc...