Harris County Logo
File #: 24-5579    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/4/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of change in contract No. 3 with Lecon, Inc. for the Zube Storm Water Detention Basin Phase 3, adding 96 calendar days (Little Cypress Creek Watershed, Bond ID F-27, Project ID L500-01-00-E003, Job No. 21/0240, Precinct 4).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): L500-01-00-E003
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Lecon, Inc. for the Zube Storm Water Detention Basin Phase 3, adding 96 calendar days (Little Cypress Creek Watershed, Bond ID F-27, Project ID L500-01-00-E003, Job No. 21/0240, Precinct 4).
end

Background and Discussion:
The Zube Storm Water Detention Basin will help alleviate flooding in the Little Cypress Creek watershed. This change in contract is needed to complete the construction contract for this project. A contract modification is necessary to adjust plan quantities for several items and to add 96 days to the contract duration, 62 days due to inclement weather, and 34 days for additional scope of work. Quantity deductions for items no longer needed have been made to offset the costs associated with the additional scope.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item ...

Click here for full text