Department: Pollution Control Services
Department Head: Latrice Babin, PhD
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Pollution Control Services (PCS) Equipment Replacement and Additions
Project ID (if applicable): N2002
Vendor Legal Name (if applicable): Multiple Vendors
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Managing Entity: Pollution Control
Incremental Authorization Requested: $2,130,000
Total Estimated Project Cost: $5,000,000 (FY25-FY27)
Request Summary:
title
Request for approval of a Final Investment Memo for the Pollution Control Services (PCS) Equipment Replacement and Additions project for an additional $2,130,000 for a FY25 authorization of $2,423,000.
end
Project Description:
Procure specialized up-to-date air monitoring, communications, emergency response, field monitoring, and lab equipment to expand laboratory testing capacity and build redundancy to ensure service continuity. The project procures specialized analytical equipment that will be able to perform new required tests, such as monitoring equipment for both air quality and water quality programs. As noted above, the court is only asked to approve FY2025 funding.
Project Scope:
The funding will replace equipment that had reached the end of its warranty, was deteriorating, and was no longer usable. This equipment will expand and fortify the lab, update the existing air monitoring network, and provide new communications, emergency response, and field team equipment.
The below tables show the status of requests for the second and third years of the five-year plan.
Table 1. Purchases started in FY2023, pending completion in FY2024.
Division
Equipment Name
Equipment Description
Cost ($)
Air Monitoring
Generator and new A/C unit
Equipment for RAAM
$10,000
Tota...