Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 230187
Vendor/Entity Legal Name (if applicable): NBG Constructors, Inc. (assignor) and Main Lane Industries, Ltd. (assignee)
MWDBE Contracted Goal (if applicable): 25%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of the order permitting the assignment of a contract with NBG Constructors, Inc. (assignor) to Main Lane Industries, Ltd. (assignee) for construction of a pedestrian bridge near The Hill at Sims Park for Precinct 1 effective April 23, 2024 (230187), MWDBE Contracted Goal: 25%.
end
Background and Discussion:
Contract 230187 was awarded to NBG Constructors, Inc. on 8/8/2023. Main Lane Industries Ltd. purchased NBG Constructors, Inc. therefore the contract will be transferred to Main Lane Industries, Ltd.
Expected Impact:
Project will proceed.
Alternative Options:
None
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
x Public Health
_ Transportation
_ Flooding
x Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
8/8/2023 |
275 |
Contract Awarded |
Location:
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 4/23/2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Mike Chang, Engineering, Jared Abbey, Senior Buyer, Harris County Purchasing
Attachments (if applicable): Letter