Department: County Engineer
Department Head/Elected Official: Milton Rahman, PHD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 22101MF2F801
Vendor/Entity Legal Name (if applicable): Terracon Consultants Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Terracon Consultants Inc. for Professional Engineering Services in connection with construction materials testing and related services for Deussen, Eisenhower Parks and West Canal Pedestrian Bridge Improvements, UPIN 22101MF2F801, Precinct 1.
end
Background and Discussion:
The project is to construct waterfront structures, pedestrian bridge, parking lot, boardwalk, trail, parking lot, lighting and landscape in both Deussen and Eisenhower Parks. It also includes the construction of a two span, signature pedestrian bridge with parapet panel crossing West Canal between Deussen and Eisenhower Parks.
Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, and other various construction materials to ensure the material’s compliance with Harris County Engineering Department’s adopted standards and specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X_ Public Health
X Transportation
_ Flooding
_ Environment
X_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
01/28/20 |
NA |
Agreement with Scientech Engineers to design West Canal Pedstrian Bridge |
08/24/21 |
21-4470 |
Amendment 1 to Agreement with Sceintech Engineers |
01/31/23 |
23-0665 |
Amendment 2 to Agreement with Sceintech Engineers |
01/25/22 |
22-0408 |
Agreement with Cobb, Fendley & Assoc to design Deussen/Eisenhower Park improvements |
Location: Deussen and Eisenhower Parks
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
Professional Services - CMT |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date April 23, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., Senior Director of Capital Project Infrastructure, HCED
Attachments (if applicable): N/A