Title: Request for approval to reduce retainage by 2.0% (from 5% to 3.0%) on Contract 351 for Third Coast Services, LLC, for improvements to the Sam Houston Tollway between US 290 and IH 45N, consisting of the installation of High-Mast Illumination (Precincts 1 and 3). Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: Toll Road Authority

Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Contract 351

Vendor/Entity Legal Name (if applicable): Third Coast Services, LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to reduce retainage by 2.0% (from 5% to 3.0%) on Contract 351 for Third Coast Services, LLC, for improvements to the Sam Houston Tollway between US 290 and IH 45N, consisting of the installation of High-Mast Illumination (Precincts 1 and 3). Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

Contract No. 351 is the replacement of 189 existing barrier‐mounted light fixtures and 3 existing high mast poles on Sam Houston Tollway, between US‐290 and IH‐45N with 81 LED high mast light fixtures, along with the replacement of electrical services throughout this corridor. The project is substantially complete, with only minor work on the original scope accompanying added scope of work left to be performed. As such, the Contractor has requested and HCTRA concurs that the retainage on the project be reduced. The release of only 2% of retainage will cover any expenses identifies as part of the project closeout. 

 

Expected Impact:

No additional funding is required as the project is substantially complete. The payment of the released retainage will come from the Toll Road Authority approved funding for the project.

 

Alternative Options:

No other recommended solutions. Should this request be denied, the retainage would be released upon project final completion and the final pay estimate is processed. However, doing so may delay the Contractor’s ability to pay his sub-contractors.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

8/24/2021

141

Contract Award

 

 

 

 

Location:

Address (if applicable): N/A

Precinct(s): Precincts 1 & 3

 

Fiscal and Personnel Summary

Service Name

Engineering & Construction Service

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: April 23, 2024

 

Anticipated Implementation Date (if different from Court date): Notice to proceed pending court approval.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 