Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 24035MF39701
Vendor/Entity Legal Name (if applicable): RDLR Architects, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for Approval to Negotiate with RDLR Architects, Inc. for designing a building to serve in the implementation of a vocational program in HCJPD Quest Program which offers opportunities for Serious Offenders to explore educational programs to learn practical skills and training necessary for specific trades, UPIN 24035MF9701, Precinct 2.
end
Background and Discussion:
Commissioners Court approved the construction of a new Jevenile Vocational Training Center on 6/27/2023. The new facility aims to improve the environments in which both youth and staff are exposed to at the Harris County Juvenile Detention Center, Harris County Leadership Academy, Harris County Youth Village, and remote facility school sites.
Expected Impact:
The program will offer opportunities for serious offenders to learn a trade which will affect the community.
and themselves in a positive way.
Alternative Options:
Alignment with Goal(s):
_X_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
06/27/223 |
163 |
Approved Juvenile Justice Facility Improvements and Modernization |
Location:
Address (if applicable): 9120 Katy Hockley Road, Katy, TX 77493, HCJPD
Precinct(s): Countywide
Fiscal and Personnel Summary |
Service Name |
9120 Katy Hockley Road, Katy, TX 77493, HCJPD |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Other |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Other |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: April 23rd, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Ross Hosket, P.E., CFM, Env SP, Interim Director of
Capital Project Facility Division, Harris County Engineering Department
Attachments (if applicable): N/A