Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24104MF38501
Vendor/Entity Legal Name (if applicable): B2Z Engineering, LLC
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with B2Z Engineering, LLC, in the amount of $421,192.15 for Professional Engineering Services for the Sidewalk - South Mason Road from Kingsland Blvd to County Line project, UPIN 24104MF38501, Precinct 4, MWDBE Contracted Goal: 19.6%.
end
Background and Discussion:
This project is around 3.5 Mile sidewalk throughout the Cornerstones and Memorial Municipal Utility Districts (MUD) area to include ADA compliant traffic elements at all public street intersections, properly sloped driveways and retaining walls where steep grades behind the curb requires it. The project improves transportation and safety measures along the project limits.
Expected Impact:
Project is needed to provide alternative mobility and connectivity options for park, school and neighborhood pedestrian and bicycle mobility and connectivity.
Alternative Options:
If no action is taken, existing conditions will continue.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
12/05/2023 |
55 |
Authorization to Negotiate |
Location:
Address (if applicable): South Mason Road, Katy
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
Engineering |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
1070 - Mobility Fund |
$ |
$421,192.15 |
$ 421,192.15 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$421,192.15 |
$ 421,192.15 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$421,192.15 |
$ 421,192.15 |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: April 23, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Agreement